Landfill Projects completed works for one of our clients on a large scale HDPE Pipework project.  The project involved:-

  • Supply and installation of a 550 meter 315mm Ring main link back to the Gas Engines.
  • Supply and Installation of a 400 meter  250mm internal gas main link.
  • Supply and installation of a 100 meter  250mm pipe to join two internal ring mains
  • Removal and relocation of four gas manifolds.
  • Supply and installation of two new gas manifolds.
  • Installation of a new condensate Knock Out Pot.
  • Installation of road crossing through site haul road.