Pine Lake Resort, Carnforth

2023-12-05T16:37:52+00:00

Pine Lake Resort, Carnforth LFP have completed the installation of a culvert system Pine Lake Resort, Carnforth. LFP implemented a new culvert system to reduce the risk and impact of flooding to the surrounding lodges. The project included a replacement of a hydraulically inadequate culvert with a box culvert including new upstream and [...]

Leachate System Improvement Works, South East Scotland

2020-12-23T13:56:33+00:00

Leachate System Improvement Works, South East Scotland Landfill Projects successfully completed leachate system improvement works at a landfill site in the South East of Scotland. Works involved both leachate and MEICA works; • Removal of the existing temporary Leachate Extraction System Pipework and air pumps • Stockpiling of redundant unusable pipework • Installation [...]

Blaguegate – Flexible Generation Plant Construction

2020-12-23T15:20:43+00:00

Blaguegate - Flexible Generation Plant Construction Landfill Projects were contracted by Ylem Energy to construct the flexible generation plant compound at Blaguegate, Skelmersdale. Works comprised of:- Excavation, separation and removal of contaminated arisings Construction of bespoke concrete plinths, and bespoke concrete forms to house wooden sleepers in order to accommodate the natural-gas-fuelled generators. Installation [...]

Capping Project, Whinney Hill Landfill, Lancashire

2020-12-17T11:57:21+00:00

Capping Project, Whinney Hill Landfill, Lancashire Following on from the successful completion of the 2018/2019 - 23,000m2 1mm geomembrane temporary cap and wind anchorage geotextile installation, Landfill Projects were awarded the 2019/2020 - 15,000m2 1mm geomembrane temporary cap and wind anchorage geotextile works. Works are now finished having been completed in challenging conditions with [...]

GCL Installation, Albion, Derbyshire

2018-11-21T20:16:24+00:00

GCL Installation, Albion, Derbyshire Landfill Projects were commissioned by G A Smith to complete the installation of 27,000m² Geosynthetic Clay Liner at Albion Landfill Site. Due to the time of year, the works were scheduled intermittently to coincide with favourable weather conditions.  Our highly experienced Lining Division worked closely with our client to ensure [...]

Odour Control Project, Lancashire (Phase 2)

2018-10-23T14:23:41+01:00

Odour Control Project, Lancashire (Phase 2)   Following works carried out under Phase 1 of this project, one area of site remained susceptible to H²s outbreak.  The uncapped area was an extremely steep banking. Lining of the steep descent presented a challenge in terms of designing a method of installation that ensured [...]

Odour Control Project, Lancashire (Phase 1)

2018-10-23T13:20:21+01:00

Odour Control Project, Lancashire (Phase 1) Following installation of a Gas Collection System for the site's Gas Operators, we were requested to provide assistance with odour control issues encountered by our client as a result of  an aggressive H²s outbreak. We conducted an assessment of the source and  current extent of the [...]

Landfill Remediation, Loughborough

2018-10-22T23:03:16+01:00

Landfill Remediation, Loughborough Landfill Projects were contracted by Veolia to complete remediation works to Mount Sorrell Landfill Site, Loughborough, comprising:- Decommissioning and removal of Gas Flare Decontamination and removal of redundant Treatment Plant Installation of new Mains Electric Feed Completion of all Civils work re construction of Compound Diversion of existing Gas [...]

Load More Posts
Go to Top